Site visit: Smart Power Plant Supervisor with integrated battery control

Author: J L Drommi

View downloads

Report from the Vogelgrün Run-of-river site visit that has been organised on Thursday, June 9, 2022.

Vogelgrun is a run-of-river hydropower plant equipped with four 39 MW Kaplan units. For the XFLEX HYDRO demonstration, one of the units is hybridised with a Battery Energy Storage System (BESS).

Download the report below.